    Limited company of equipment of environmental protection of Zhejiang grand rich is a major is engaged in off-gas treatment, dust processing, manufacturer of equipment of spray paint room, small today make up introduce to everybodyOff-gas treatment equipmentGush drenchs the installation note of the tower:

     

    Gush drenchs tower

    1, make good treatment to construction material, as far as possible managing steel tube, because the span of shower nozzle is 3.2-3.6 rice commonly, and steel tube is 6 meters of scale, such is about that calculate the use quantity of good steel tube, only the managing ability that use a pipe has beneficial result. Machining conduit while want best number, when be being installed so, meet spare time.

    2, partial personnel can be arranged to install conduit to raise hanger when conduit is machined, had machined so can install directly simply. The director is installed to first after raising hanger installation to end, will assemble in the ground simply as far as possible after finishing, join with director path again. So OK and economic artificial.

    3, the attention is safe, headroom works and use electric security, prevent mechanical harm (curium without tine, the machine that cover silk and the machine that press groove) the deepness that when pressing groove, notices to press groove and appearance, avoid to machine unqualified cause slack, also want to note a quality that buckle likewise. After net installation ends, the canal must have conduit compression test, keep the net does not leak truly.

    4, when cooperating other and professional construction, must notice finished product is protected, decorate construction to a string of 1 must drench gush the place of the head leaves hole when the top, do not want leakage to install gush to drench first.

    After systematic setup ends, must undertake linkage experiments, ensure the system moves normally. Wet call the police installation of a powerful person should undertake installing according to the manual, avoid to install error. Installation is to should notice to adjust gush to drench the rotational direction of pump, with the installation direction of one-way a powerful person on conduit.

    Above isSmall today arrange the off-gas treatment facility that gives everybody introductionGush drenchs the installation note of the tower hopes pair of everybody are helpful. More about off-gas treatment equipment, gush drenchs the product information of the tower, greeting incoming telegram seeks advice from us.